Knock Down Rebuild: The Full Sequence

The demolition is three days in the middle of a much longer process. Getting the order right is most of what separates a smooth rebuild from an expensive one.

Updated 2026-09-10 · 8 min read

The whole sequence, in order

Most people picture a knock-down rebuild as demolition, then building. The demolition is actually a short event surrounded by a lot of preparation, and the preparation is where the timeline lives.

  1. Site investigation. Survey, soil test, service locations. Some of this feeds the demolition scope and all of it feeds the build.
  2. Design and builder selection, running in parallel with everything below.
  3. Planning certificate — establishes the demolition approval pathway.
  4. Hazardous materials survey if the house is pre-1990. In the Illawarra, assume it is needed.
  5. Demolition approval lodged — CDC or DA depending on the property.
  6. Service disconnections initiated. Start these early; electricity abolishment is the long pole.
  7. Asbestos removal by a licensed removalist, if the survey requires it.
  8. Demolition — two to four days.
  9. Site left to the agreed standard.
  10. Building approval and construction.

Steps 3 through 7 overlap heavily. Run sequentially they take months; run in parallel, four to eight weeks is realistic for a straightforward house.

The three things to agree with your builder first

This is the part that saves the most money, and it happens before the demolition is even quoted.

What level should the block be left at? "Cleared" is not a standard. A block ready for a surveyor to peg is a different finish to a block that simply has no house on it. Get a nominated level or a clear written description into the demolition scope.

Does the slab go, and to what depth? In a rebuild, almost always yes — but say so, and include the footings and edge beams. Those sit below the visible slab and are the single most common thing discovered by whoever excavates next. Concrete removal covers how it is priced.

What stays? Retaining walls, fences, established trees, the driveway, a shed you want to keep. Every one of these is a scope decision, and each is expensive to reverse. Trees in particular are a separate approval and cannot be removed under a demolition consent.

Getting these three into the demolition quote costs nothing. Discovering them afterwards costs a variation at a point where the machine has already left.

Where the weeks actually go

Stage Realistic duration
Planning certificate days
Hazardous materials survey 1–2 weeks including lab time
Demolition approval (CDC) weeks
Demolition approval (DA) considerably longer
Service disconnections 3–6 weeks, electricity longest
Asbestos removal + clearance 1–2 weeks where required
Demolition itself 2–4 days

The demolition is the shortest item on the list. Everyone plans it and underestimates the rest.

The Illawarra specifics

Access sets the price. The narrow strip below the escarpment produces genuinely constrained sites — Thirroul, Bulli, Corrimal and the older parts of Wollongong and Port Kembla. Smaller machines, more truck movements, sometimes street loading under permit. Newer land through Dapto, West Dapto and Shellharbour is far more straightforward and prices accordingly.

Assume asbestos. The post-war fibro housing across the region means a pre-1990 house should be treated as containing asbestos until a survey says otherwise. This is the biggest single variable in both cost and program. See asbestos in Illawarra homes.

Five councils, five processes. Wollongong, Shellharbour, Kiama, Wingecarribee and Shoalhaven each have their own controls. Advice from a job in one does not transfer to another.

Growth-area covenants. On newer estates, developer design guidelines can sit alongside the council process.

Capture the site information while you can

Once the house is down and before the new work starts, the site is more legible than it will ever be again.

Photograph and record the sewer junction position, the water main entry, the electricity point of attachment, and the levels. Keep the survey. Keep the hazardous materials report and the asbestos disposal documentation.

That file costs nothing to assemble and saves real money at the build stage — and a future buyer's inspector may well ask for the asbestos records.

The neighbours

On tighter Illawarra blocks the adjoining house can be very close. Expect hoarding along shared boundaries, protection or removal of shared fencing, dust suppression, and often a dilapidation report on adjoining properties before work starts.

That report is a documented record of the neighbour's existing condition, and it protects you as much as them. Without one, any pre-existing crack next door can become your problem.

Tell the neighbours what is happening and roughly how long it will take. It costs nothing and prevents most of the disputes that arise on residential demolition.

The costs people forget to budget

Beyond the demolition and the build, a knock-down rebuild carries a set of intermediate costs that surprise first-timers.

Somewhere to live. The gap between moving out and moving in is longer than the construction program, because it includes the demolition lead time at the front and the finishing at the back. Rent for that period is frequently the largest unbudgeted item in the whole project.

Storage. For whatever does not come to the rental.

Two lots of moving. Out, and back in.

Holding costs. Rates, insurance and any loan interest continue on a block with no house on it.

Site costs at the build stage. Soil conditions, levels and service positions can all add to the slab and footing costs, and they are only fully known once the block is clear.

None of these are demolition costs, but they all sit inside the demolition timeline, which is why compressing the lead time has value beyond convenience.

Finance and insurance during the gap

Two administrative items sit awkwardly in the middle of a knock-down rebuild and are easy to overlook.

Insurance. Once the house is gone you are insuring vacant land, not a dwelling, and then a construction site. Those are different policies. Tell your insurer before the demolition rather than after, and check who carries the risk during the demolition itself — the contractor's public liability covers their work, not your land.

Finance. If there is a mortgage, the lender has security over a property that is about to have its main improvement removed. Construction loans handle this routinely, but the lender needs to know the plan, and the drawdown schedule usually keys to build stages that only start after demolition.

Neither is difficult. Both are much easier to arrange in advance than to explain afterwards.

One decision worth making early

Decide whether you are demolishing to rebuild or demolishing to sell. It changes the scope.

A block being sold wants to look presentable and be safe — level, clear, tidy, fenced. A block being built on wants to be at a nominated level with the slab and footings gone, services identified, and clean enough for a surveyor.

They are different finishes at different prices, and the second is not automatically included in the first. Say which one you are buying.

Getting a price

The cost bands cover the numbers, how quotes are built covers reading one, and house demolition covers the work itself.

Call 02 4214 4202 or send the site details through — and if you have a builder already, tell us what they want the block to look like.

FAQs

Frequently asked questions

How long does the demolition stage of a knock down rebuild take?

Two to four days on site for a typical house. The realistic lead time in front of it is four to eight weeks, covering the approval pathway, service disconnections and any asbestos removal. Those run in parallel, which is what keeps the total down.

Should the slab come out?

Almost always in a rebuild, because the new structure needs its own footings and the old slab is in the way. Confirm it explicitly in the demolition scope, and confirm the footings and edge beams are included too — those are the classic omission.

What level should the block be left at?

Whatever your builder specifies. This has to be agreed before the demolition is quoted, not after. 'Cleared' and 'level to a nominated height, ready for a surveyor to peg' are different standards at different prices.

Can demolition and the building approval run at the same time?

Frequently, yes, and it is usually the right approach. Demolition often has its own approval pathway separate from the new dwelling, so the block can be cleared while the building design is finalised or assessed. Confirm the sequencing with your certifier.

What about the driveway and the crossover?

The driveway inside the boundary is part of the demolition scope if you want it gone. The crossover between the boundary and the road usually sits on public land, carries council requirements and is often handled at the building stage rather than the demolition one.